Free C_TS412_1909 Sample Questions and 100% Cover Real Exam Questions (Updated 82 Questions)
Download Real SAP C_TS412_1909 Exam Dumps Test Engine Exam Questions
SAP C_TS412_1909 Exam Description:
The "SAP Certified Application Associate - SAP S/4HANA Project Systems" certification exam verifies that the candidate has the fundamental and core knowledge in the area of sourcing and procurement required for the consultant profile. This certificate proves that the candidate has an overall understanding and can implement the knowledge practically in projects to contribute to the success of the planning and implementation phases in a mentored role. Previous project experience is not necessarily a prerequisite to pass this exam.
NEW QUESTION 11
Which of the following statements apply to project versions? Note: There are 2 correct Answers to this question.
- A. Project versions are mandatory for Milestone Trend Analysis (MTA).
- B. Project versions can be created automatically based on user status.
- C. Project versions can be changed.
- D. Manually created project versions always require a project version profile.
Answer: A,C
NEW QUESTION 12
Where do you control whether a project stock is managed as valuated or non-valuated project stock?
- A. In the project definition
- B. In the network activity
- C. In the WBS element
- D. In the material master
Answer: A
NEW QUESTION 13
What functions are available for period end closing in SAP Project System? Note: There are 3 correct Answers to this question.
- A. Results analysis
- B. Settlement
- C. Milestone trend analysis
- D. Confirmations
- E. Progress analysis
Answer: A,B,E
NEW QUESTION 14
Which of the following is visible in the project planning board? Note: There are 2 correct Answers to this question.
- A. Maintenance orders assigned to an activity
- B. Project-relevant purchase orders
- C. Production orders assigned to WBS elements
- D. Capacity requirements
Answer: A,D
NEW QUESTION 15
You are working with predefined project coding masks to create projects. Which of the following statements apply? Note: There are 2 correct Answers to this question.
- A. You can shorten the project mask even when there are existing projects.
- B. You can only use numbers for a project coding mask definition.
- C. You can use the same coding mask for standard projects and operative projects.
- D. You can use an indicator to determine that only coded project numbers may be used within SAP Project System.
Answer: C,D
NEW QUESTION 16
What PP/DS master data is necessary for using PP/DS? Note: There are 2 correct Answers to this question.
- A. Material
- B. Resource
- C. Location
- D. Production version
Answer: B,C
NEW QUESTION 17
Where can you define a network as "header-account-assigned" or "activity-account-assigned"?
- A. Parameters for the network type
- B. Network profile
- C. Network type
- D. Project profile
Answer: A
NEW QUESTION 18
What are valid procurement types for stock items? Note: There are 3 correct Answers to this question.
- A. Third-party order
- B. Purchase requisition and Reservation for WBS element
- C. Preliminary purchase requisition for WBS element
- D. Planned order
- E. Reservation for WBS element
Answer: B,C,E
NEW QUESTION 19
You plan an activity that starts on February 1 and finishes on February 28. For this activity, you want to define a milestone for February 10 which should NOT be changed through scheduling. What do you recommend for milestone definition?
- A. Enter an offset of 10 days to the start date of the activity.
- B. Enter an offset of -18 days to the finish date of the activity.
- C. Enter 10 days as duration.
- D. Enter February 10 as fixed date.
Answer: D
NEW QUESTION 20
You want to use billing for a customer project. Which customizing object controls the billing of sales order items?
- A. Requirements type
- B. Requirements class
- C. Schedule line category
- D. Item category
Answer: D
NEW QUESTION 21
You have created an internally-processed network activity, and assigned a work center and the work.
After saving, you discover that no planned costs are displayed in the cost element report for the activity.
What could be the reason? Note: There are 3 correct Answers to this question.
- A. The duration is missing in the activity.
- B. The formula for costing in the work center is incorrect.
- C. Integrated planning for the network is active.
- D. The activity output price for the activity type and cost center assigned to the work center is not maintained.
- E. The Determine Costs indicator in the network header rules out planned cost calculation.
Answer: A,D,E
NEW QUESTION 22
What are the prerequisites for delivering materials from the project? Note: There are 2 correct Answers to this question.
- A. A sold to party is necessary.
- B. A shipping point is necessary.
- C. A sales order must be created in advance.
- D. A delivery document type must be configured.
Answer: A,B
NEW QUESTION 23
You have activated the workflow for confirmation variances in SAP Project System. Who is the receiver of this workflow item?
- A. The MRP controller for the network
- B. The person responsible for the work center
- C. The person responsible for the network activity
- D. The person responsible for the superior WBS element
Answer: A
NEW QUESTION 24
Budgeting is implemented for projects. The budget has been adjusted several times. What standard report type provides an overview of adjustments on the budget?
- A. Cost element report on budget updates
- B. Line item report for budgets
- C. Structure overview for budgets
- D. Hierarchical report on budget updates
Answer: B
NEW QUESTION 25
Where do you maintain the length of the project ID?
- A. Project coding mask
- B. Project profile
- C. Project type
- D. Special characters
Answer: A
NEW QUESTION 26
How can you search in the structure overview based on the user status? Note: There are 2 correct Answers to this question.
- A. By searching for the individual status
- B. By searching via status combination code
- C. By searching via status selection profile
- D. By searching for the status profile
Answer: A,D
NEW QUESTION 27
A service company uses project management and they complain that the system does not prevent their project managers from exceeding their budgets. What actions do you have to take to solve the problem?
- A. Activate availability control for the WBS elements. Define the tolerance limits on each WBS element.
- B. Activate commitment management in the project definition. Enter the budget in the master data of the top WBS element.
- C. Activate availability control in the assigned budget profile. Define the tolerance limits in customizing.
- D. Activate availability control for projects in the controlling area. Enter the plan data for each WBS element.
Answer: C
NEW QUESTION 28
......
C_TS412_1909 Exam Certification Details:
| Duration: | 180 mins |
| Level: | Associate |
| Sample Questions: | SAP C_TS412_1909 Exam Sample Question |
| Languages: | English |
| Exam: | 80 questions |
| Cut Score: | 51% |
SAP C_TS412_1909 Certification Exam Topics:
| Topic Areas | Topic Details, Courses, Books |
|---|---|
| Resources > 12% | Describe how the Resource Planning process integrates with HCM |
| Cost and Budgets > 12% | Describe procedures for establishing budgets and reporting costs. |
| Material > 12% | Explain Work breakdown structure BOM, BOM PS Interface, component assignment in the network, material procurement |
| Dates > 12% | Describe the importance of various dates which can be tracked for projects |
| Project Structures > 12% | Name the components of Work Breakdown Structure, Network and activities, Milestones |
| Reporting < 8% | Determine general reporting requirements and reporting requirements for cost centers. Configure cost center reporting and create report painter reports |
| Revenues and Payments > 12% | Describe the characteristics of Revenues & Payments. |