NEW QUESTION # 23
What was the original planned duration for Activity A through Activity G?

  • A. 24.
  • B. 25.
  • C. 28.
  • D. 26.

Answer: C


NEW QUESTION # 24
What does the narrow band at "Y" represent?

  • A. A rework period.
  • B. Activity inactivity.
  • C. You cannot tell with the information supplied.
  • D. Resource limitation period.

Answer: B


NEW QUESTION # 25
In its simplest form, what is the main drawback of critical path method scheduling?

  • A. It doesn't account for interdependent between activities.
  • B. It allows for Precedence Diagramming Method to be used in place of Arrow Diagramming Method.
  • C. It requires a backward pass to calculate late dates.
  • D. It assumes that resources are unlimited.

Answer: D


NEW QUESTION # 26
If the administrative constraints for developing the precedence diagram, as provided in the contract documents, indicate that no individual construction activities shall have a longer duration of two months, how many activities in the "normal" schedule would be affected?

  • A. 12.
  • B. 14.
  • C. 13.
  • D. Cannot be determined.

Answer: A


NEW QUESTION # 27
Assuming a total of 30 lifts per crane per day, what is the maximum number of lifts that could be accomplished using 3 small tower cranes over a 5-day period?

  • A. 450 lifts
  • B. 300 lifts
  • C. 150 lifts
  • D. 45 lifts

Answer: A


NEW QUESTION # 28
During proofing of the product manual, a problem was discovered requiring 15 days additional time to effect a correction. How can the date of availability be maintained?

  • A. Expedite packaging by 5 days.
  • B. Delay manufacturing by 5 days.
  • C. Delay product release by 5 days.
  • D. Expedite printing by 5 days.

Answer: C


NEW QUESTION # 29
Which of the following is NOT a tool or technique used to perform scope planning?

  • A. Schedule performance indexing.
  • B. Alternatives identification.
  • C. Benefit cost analysis.
  • D. Expert Judgment.

Answer: A


NEW QUESTION # 30
Project delays are best analyzed

  • A. Late in the project.
  • B. Contemporaneously with the delay.
  • C. After either the contractor or the owner acknowledges ^responsibility for the delay.
  • D. By an expert after the project is finished when complete records are available and the impact is known.

Answer: D


NEW QUESTION # 31
What is the actual duration as of the status date or data date of Activity B?

  • A. 7.
  • B. 0.
  • C. 4.
  • D. 3.

Answer: D


NEW QUESTION # 32
Time-scaled logic diagrams are

  • A. Logic networks that are drawn to match the calendar.
  • B. Only calculated using a computer.
  • C. The same as a pure-logic diagram.
  • D. Used to calculate the most probable activity duration.

Answer: A


NEW QUESTION # 33
Which statement is true?

  • A. Where compensability cannot be established, excusability is assumed.
  • B. Where compensability can be established, excusability is assumed.
  • C. Where compensability can be established, excusabltity cannot be assumed.
  • D. Where compensability cannot be established, excusability is a given.

Answer: A


NEW QUESTION # 34
Which of the following is NOT required when initially planning a project?

  • A. Resource Identification and leveling.
  • B. A schedule that identifies tasks required on a project.
  • C. The duration of each task.
  • D. Logical relationships between the tasks.

Answer: C


NEW QUESTION # 35
Why does activity 1001 have two successor activities?

  • A. Because the late finish of 1001 and the late start of 7001 require two successors
  • B. Because the problem could not effectively work with only one successor
  • C. Because the duration of activities 2001, 2002 and 200.f require two successors
  • D. Because there are two defined logic paths for the work

Answer: D


NEW QUESTION # 36
What is the remaining work duration of Active D?

  • A. 3.
  • B. 8.
  • C. 4.
  • D. 0

Answer: C


NEW QUESTION # 37
If drafting of the product manual overruns its planned duration by 5 days, how many days may the manufacturing be delayed without affecting release of the product?

  • A. 0 days.
  • B. 10 days.
  • C. 5 days.
  • D. 15 days.

Answer: A


NEW QUESTION # 38
Which of the following will always describe the critical path? The path with

  • A. Negative float.
  • B. The longest duration through the network.
  • C. The shortest duration and negative float.
  • D. Zero float.

Answer: D


NEW QUESTION # 39
Using the "normal" schedule, and assuming you are billing on the last day of the month for previous month and for appropriate partial months, how many invoices will you have for this project?

  • A. 37.
  • B. 40.
  • C. 42.
  • D. 36.

Answer: D


NEW QUESTION # 40
What is the cycle time?

  • A. 17 minutes
  • B. 14 minutes
  • C. 6 minutes
  • D. 5 minutes

Answer: A


NEW QUESTION # 41
Using the "normal" schedule, if you start Activity 7001 on April 1, 2002, and using a 5-day workweek, what the finish date for Activity 7001?

  • A. 06-05-02.
  • B. 06-18-02.
  • C. 06-04-02.
  • D. 06-11-02.

Answer: A


NEW QUESTION # 42
Budgeted cost of work scheduled is _______________________.

  • A. The value of the completed work expressed in terms of the budget assigned to that work
  • B. The total authorized budget for accomplishing the project scope
  • C. The expected total cost of an activity, group of activities or the project
  • D. The sum of all budgets for work scheduled to be accomplished within a given time period

Answer: C


NEW QUESTION # 43
An early start constraint dictates

  • A. The actual start of an activity.
  • B. The planned start of an activity.
  • C. The planned start of a successor activity
  • D. An activity's remaining duration.

Answer: C


NEW QUESTION # 44
......